Engineering planning implementation

Industry
€0,5 bln Mega Yacht builder building the biggest yachts of the Netherlands.

Challenge
Chaotic and ad-hoc Engineering process causing a lot of rework and project delays.

Project
Design and implementation of a level 2 and level 3 Engineering planning for planning & control of the Engineering process for the yard and it’s contractors.

Results

  • Planning templates reducing the planning setup time from 6 months to 1 day.
  • 3 months lead time reduction (start Basic Engineering to Delivery).